The Auditor General has shed new light on the four-year delayed completion of the 23-kilometre Busega-Mpigi expressway, revealing challenges that have stalled progress.
Last week, the ministry of Works and Transport confirmed that the completion deadline for the project has been extended to 2027. This represents a four-year delay from the original schedule. The ministry attributed the delay to complexities in land compensation, limited resources, and the disruptions caused by the COVID-19 pandemic.
The expressway, implemented by China Civil Engineering and Construction Corporation (CCECC), was initially projected to cost $151 million (approximately Shs 547 billion). Funding for the project is provided by the African Development Bank (AfDB) and the African Development Fund (ADF).
The ministry puts the work progress at about 45 per cent. However, the report by the Office of the Auditor General (OAG) 2024 shows that there has been a significant escalation of costs as well as payment shortfalls, mainly coming from inadequate preparation.
“Busega-Mpigi Expressway project is facing significant shortcomings in technical preparation and funding management,” says the report, adding that the cost has since more than doubled.
Initially contracted at Shs 547.5 billion, which the report says was reached without adequate detailed designs, subsequent revisions have raised the project cost to Shs 1.35 trillion as of May 2023. Consequently, by May 2024, the original contract funds for civil works were fully depleted, and, the OAG says that by then, physical progress was at only 40.86 per cent.
As if that was not enough, the works so far completed at the time and certified, presented payment arrears of Shs 30.8 billion. These accumulations pose “risks of delayed payments and legal claims” by the contractor, according to the report.
As of July 2024, progress had reached just 42.28 per cent, falling short of targets, with the completion date extended to September 2027. With an addition of 2 per cent per month, there is fear that even the new deadline might not be met.
“Delayed payments, unplanned costs, and funding shortfalls threaten timely completion and cost containment,” says the AG, advising the government to quickly look for resources to expedite the works.
“I advised the accounting officer to expedite efforts to secure additional funding to meet contract obligations and reduce risks of payment delays and contractor accumulation of interest claims on delayed payments.”
Accumulation of delayed payments as well as escalation of costs has been one of the main impediments to the progress of road and bridge works, by the Uganda National Roads Authority (UNRA), which has recently been reintegrated into the ministry.
This trend has seen many road projects either slow down or temporarily suspended by the contractors as they await the disbursement of funds by the government. For example, under the Integrated Transport Infrastructure and Services (ITIS) programme, as of June 30, 2024, arrears amounting to Shs 798.97 billion remained unpaid for road and bridge construction projects.
These arrears include Shs 789.48 billion under UNRA and Shs 9.49 billion under the ministry of Works and Transport.
“The above indicates inadequate budgeting practices and exposes the government to potential litigation and financial penalties due to delayed payments,” says Edward Akol.
For instance, UNRA, the report shows, incurred interest charges totalling Shs 27.66 billion on overdue Interim Payment Certificates (IPCs) that were not settled within the agreed timelines. These delays resulted in an average daily interest payment of Shs 75 million and a monthly loss of Shs 2.305 billion.
These interest costs were unbudgeted for during the financial year and diverted critical funds away from UNRA’s core mandate of executing road construction projects, concluded Akol.

For instance, UNRA, the report shows, incurred interest charges totalling Shs 27.66 billion on overdue Interim Payment Certificates (IPCs) that were not settled within the agreed timelines.
These delays resulted in an average daily interest payment of Shs 75 million and a monthly loss of Shs 2.305 billion…This indicates that Uganda at this time in 2025 is an Industrially Developed Country with Surplus Funds to squander!..Being Run by a Family cum Mafia Clan with Private Armies aiming at Killing,Maiming and Abductions of Innocent Folks only to End up battered and Castrated! The Late Ssegirinya was an Example!