Finance minister Matia Kasaija has expressed worry over the delays that ongoing infrastructural projects are currently experiencing. 

The delays have increased the cost of the projects and contributed to the debt overload that the country is grappling with. The minister lamented that the issue of land has seen government pay huge sums of money in compensation.

“I have tasked the Unra ED [Allen Kagina]… I want her to give me how much we are spending on each road in terms of land compensation versus the cost of actually doing the work,” Kasaija said.

“Land acquisition in Uganda today is a thorn in the flesh on infrastructural development. So many projects have been delayed because of land acquisition,” he fumed. He was speaking during the signing of a loan agreement with the African Development Bank (AfDB) for the construction of the 23km Busega-Mpigi expressway and Kagitumba-Kayonza-Rusumo roads.

For instance, a disputed rock along the Kampala-Entebbe expressway made contractors experience long delay due to misunderstandings between the landowners and Unra over compensation.

Also, this year, government plans to start the resettlement action plan in Bunyoro where the crude oil pipeline will pass. However, both the government and residents have not reached consensus on how much payment will be given to those who will be displaced from their land.

Finance Minister Matia Kasaija (R) and the East Africa regional director at AfDB, Gabriel Negatu, at the signing ceremony

Land rows are sometimes experienced when government delays to release the money for compensation. For example, the government valuer can make an assessment of the land and advise the compensation rate.

However, sometimes it takes even more than two years for the money to be paid. By the time the money is handed out, it does not reflect the value of the land in its current state, creating a barrage of complaints. According to Gabriel Negatu, the regional director, East Africa, at AfDB, the support from the bank targets to improve the transport services in central Kampala.

Kasaija said the total cost of the project is Shs 690bn, of which AfDB will cover Shs 542bn (about 79 per cent) of the total cost. The government will cover the remaining 21 per cent (Shs 148bn) of the project cost.

Upgrade of the Busega-Mpigi road is expected to start off in 2018. Many people are likely to face evictions as the expansion works of the road starts. Officials from Unra said evaluations are still in progress to determine how many people are to face evictions.

The government through the ministry of lands plans to make amendments to the Land Act to pave way for easy acquisition of land by the government to speedup the pace in project implementation. 

The constitution states that land belongs to the people. However, Kasaija noted that if the country is to develop at the much-desired pace that is needed to reach middle income, there is need to make amendments to the Land Act.

“Land belongs to the people—which is appropriate. But lately, there is a development that is baffling me. People seem to be taking advantage in the weakness of the law,” he said.

“This is everywhere [wrangles in land] be it in electricity lines and many other things; the issue on how to agree with the landowners has become a very big headache to government,” Kasaija added.

The signing event was attended by Works and Transport minister Monica Azuba, secretary to the treasury, Keith Muhakanizi, and Allen Kagina, the executive director of Unra.