In disclosing that the Kampala-Entebbe expressway is likely to cost an extra Shs 213bn, finance minister Matia Kasaija has reignited debate on the dicey issue of compensation for land acquired for public infrastructure development.
Kasaija told a gathering of Ugandans living in the diaspora this week that due to unending compensation disputes, the 51.4km Entebbe expressway will not only cost $60m (Shs 213bn) more, it will also take much longer than the earlier planned four years.
When disputes arise, not only does the compensation bill skyrocket, the contractor is also compelled to claim large sums in damages for delays. This applies to almost all major road construction projects in Uganda.
According to the minister for lands, the government spends about $27m (Shs 96.8bn) every year in interest on unspent donor money meant for infrastructure, some of which is lying idle because of compensation disputes.
There is no denying that compensation disputes are causing unnecessary delays and raising the total cost of infrastructural development in the country.
Speculators deliberately set out to profiteer from government projects by acquiring land titles, often illegally, with an eye on outrageous sums in compensation.
This conundrum has forced government to come up with a controversial amendment to the existing land law that will make it easier for the state to acquire land in public interest.
According to the bill, where government and the landowner fail to agree on fair and adequate compensation, government will deposit in court or any other competent authority the value of the property, as determined by the government valuer, and proceed to take possession pending court’s decision.Â
We are constrained to sympathise with the government’s position. With Uganda’s infrastructure deficit, we can’t afford to lose so much money and time in project implementation.
The constitution already provides for land being owned by the people, and public land being held in trust by the government on behalf of the people. With regard to land acquisition for public works, the constitution provides for prior compensation that is fair, adequate and prompt.
While these well-intentioned provisions must be upheld, they should not be abused to hold hostage the government and the people who benefit from public infrastructure.